Important: This SWMS template is provided as a starting point only. It must be reviewed and customised to reflect the specific conditions, hazards, and controls for your workplace and task. The PCBU remains responsible for ensuring the SWMS is suitable for the specific work. This template does not constitute legal advice. Refer to your state or territory WHS regulator for compliance requirements.
Structural & Formwork

Precast Concrete Installation — Safe Work Method Statement

Safe Work Method Statement for the delivery, handling, and installation of precast concrete elements including beams, columns, stairs, and wall panels, covering crane operations, rigging, and structural connection works.

Download this template

Personal Protective Equipment

Hard hatSteel-capped safety bootsHigh-visibility vestSafety harness and lanyard (for elevated work)Safety glassesCut-resistant work gloves

High Risk Construction Work Types

  • Work involving risk of a person falling more than 2 metres
  • Work involving the use of a crane, hoist or other powered lifting device
  • Formwork or falsework

Risk Assessment

1.Precast Element Delivery and Unloading

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Element topple from delivery vehicle during unloadingCatastrophicDeliveries must be pre-planned with the crane operator and licensed rigger to confirm element weights, rigging method, and vehicle positioning before the truck arrives. The delivery area must be level, firm, and capable of supporting the combined vehicle and load weight. Unloading sequence must be coordinated so that remaining elements on the vehicle remain stable after each lift. Rigger confirms all elements have dedicated lift points before unloading commences.LowRigger / Crane Operator / Site Supervisor
Struck by swinging precast element during crane unloadingCatastrophicEstablish an exclusion zone equal to the maximum swing radius of the crane plus the longest element dimension. Control access using barriers and a banksman. Only the rigger/dogman may be within the exclusion zone during lifts. Workers not involved in the lift must remain in a designated safe zone. Use two tag lines on all elements to prevent uncontrolled swinging.ModerateDogman / Crane Operator / Site Supervisor

2.Rigging and Lifting Precast Elements

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Rigging failure due to incorrect sling selection or damaged hardwareCatastrophicAll rigging equipment must be inspected by the licensed rigger before each lift. Discard any sling, shackle, or connector showing cuts, abrasion, kinking, corrosion, or deformation. Confirm WLL markings on every component match or exceed the load. Rigging arrangement must be per the precast manufacturer's lift drawing or engineer-certified rigging plan. Record pre-lift inspection in the crane lift register.LowLicensed Rigger

3.Element Placement and Alignment

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Workers hands or feet crushed between element and supporting structureHighWorkers must never place hands or feet between a suspended precast element and its bearing surface. Use remote guidance tools (guide bars, rope guides) or sacrificial timber blocks to align elements without direct body contact. Crane operator to lower elements slowly (maximum 0.3 m/s) when within 500 mm of bearing. Workers signal 'stop' via radio/hand signal to crane operator if alignment requires adjustment; crane holds position while workers reposition with guide bars only.LowRigger / Crane Operator / All Workers
Element slipping off bearing due to inadequate bearing areaCatastrophicConfirm bearing width and length against the structural engineer's drawings before releasing from crane. Minimum bearing must be achieved on all support points simultaneously before the crane releases load. If minimum bearing is not achieved on first placement, re-lift the element and adjust the supporting structure or temporary packing. Do not use timber wedges as sole permanent bearing without engineer approval.LowSite Engineer / Rigger

4.Structural Connections and Grouting

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Chemical burns from cementitious grout or epoxy resin contactModerateWorkers handling grout or epoxy wear chemical-resistant gloves, safety glasses, and long sleeves. Review SDS for grout products before commencement. In the event of skin contact, flush with water for 15 minutes. Eye contact with grout requires immediate flushing with copious water for 20 minutes and medical assessment. Provide eyewash station within 10 metres of all grouting operations.LowAll Workers / Site Supervisor

5.Working at Height During Installation

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Falls from height when installing connections on elevated elementsCatastrophicWhere workers must access the top of precast columns or beams above 2 m, an engineered work platform (EWP, scaffolding, or MEWP) must be provided. Workers must not free-climb precast elements. If temporary platform cannot be provided, workers must wear a full-body harness attached to a certified anchor point on the element or structure. Anchor must be rated to AS/NZS 1891.4 and inspected by the site supervisor before use. Edge protection must be installed on all decks as soon as the first elements are placed.ModerateSite Supervisor / All Workers

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________

Download this template

Go paperless with WorkSignals

Manage SWMS digitally — track sign-offs, attach photos, and access everything from your phone.

Try WorkSignals free