SWMS template · Excavation & Earthworks

Retaining Wall Construction — Safe Work Method Statement

Safe Work Method Statement for the construction of retaining walls including timber sleeper, concrete block, reinforced concrete, and steel sheet pile retaining systems, covering excavation, drainage, and structural installation.

Last reviewed

Category
Excavation & Earthworks
HRCW
4 categories
Job steps
5
Hazards rated
7
PPE items
7

Retaining wall construction combines excavation hazards with structural engineering complexity and, in many cases, working at height or in deep excavations. The HRCW classification under regulation 291 of the model WHS Regulations will apply wherever the associated excavation exceeds 1.5 m depth or the work involves structural elements that could collapse. A SWMS is mandatory for all retaining wall work on construction sites, and a structural engineer's design is required for any retaining wall above 1 metre in height under the National Construction Code (NCC) and applicable state building regulations.

In most Australian states, retaining walls above 1 metre require building approval from the relevant local council before construction commences. In Queensland, retaining walls over 1 metre in height or supporting a surcharge load require a building permit and must be designed by a Registered Professional Engineer of Queensland (RPEQ). Similar requirements apply in other states under their respective building acts. The builder must be licensed for structural work — a builder's licence under the relevant state building authority (QBCC, NSW Fair Trading, VBA, etc.) covers this scope.

The excavation required for retaining wall construction must comply with the Safe Work Australia Model Code of Practice: Excavation Work. Ground collapse risk during excavation is particularly significant for retaining walls because the excavation is typically cut at or near the toe of an existing slope or embankment, which is already in a state of marginal equilibrium. A geotechnical engineer should assess the safe excavation geometry and any temporary shoring requirements before excavation commences. Before You Dig Australia (byda.com.au) must be contacted and service plans obtained, as retaining walls frequently require footings near existing utility services.

Customise this template with the wall height, wall type, and structural engineer's design reference; the excavation depth and soil type; the shoring method if applicable; and the building approval reference number. This SWMS applies in all Australian states and territories.

High Risk Construction Work Types

  • Risk of a person falling more than 2 metres
  • Work in or near a shaft or trench deeper than 1.5 metres, or a tunnel
  • Work on or near energised electrical installations or services
  • Work involving tilt-up or precast concrete

Personal Protective Equipment

  • Hard hat (Class 1)
  • High-visibility vest (Class 2)
  • Steel-capped safety boots
  • Safety glasses
  • Gloves (leather)
  • Hearing protection
  • P2 respirator (concrete works)

Risk Assessment

RatingsCatastrophicHighModerateLow

Step 1Excavation for wall footing and batter

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Collapse of retained embankment during excavationCatastrophicEngage a geotechnical engineer to assess slope stability and specify safe excavation batters or temporary shoring requirements before excavation commences. Do not steepen the batter beyond the engineer-specified angle under any circumstances. Install temporary earth anchors or king posts and lagging where engineered shoring is specified. Inspect batter face each morning and after any rain event. Evacuate workers immediately if cracking, slumping, or tension cracks appear at top of embankment. Keep all plant and heavy loads back minimum 1.5 × excavation depth from the top of excavation.ModerateGeotechnical Engineer / Site Supervisor
Falls into excavation zoneHighInstall safety mesh or barrier fencing along all open excavation edges not currently being worked. Trench or excavation edge barriers must comply with AS 1657 fall prevention requirements. Provide fixed access ladders or temporary stair units at maximum 9 m intervals. Do not allow workers to jump in or out of excavations. Clearly mark excavation edges with high-visibility tape and barriers. Review edge protection after any ground disturbance or rainfall.LowSite Supervisor / All Workers

Step 2Concrete footing pour

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Footing formwork blowout under concrete pressureHighDesign formwork in accordance with AS 3610 Formwork for Concrete. Inspect all formwork and bracing before concrete pour commences. Do not exceed recommended pour rate in formwork design. Ensure all bracing is anchored to stable substrate. Position concrete pump hose to minimise impact loading on formwork panels. Assign a dedicated formwork inspector during pour to monitor for any movement, bulging, or displacement. Immediately stop pour and relieve pressure if any formwork movement is detected.LowFormwork Supervisor / Site Supervisor

Step 3Block, sleeper, or panel installation

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Manual handling musculoskeletal injury during wall unit installationModerateConduct manual handling risk assessment for each wall unit type. Concrete retaining blocks exceeding 20 kg must be installed with mechanical lifting assistance (block clamp on excavator, telehandler, or pallet jack). Timber sleepers over 15 kg to use two-person lift minimum with coordinated lift signal. Workers must not twist during lifts — turn feet, not spine. Provide training in safe lifting technique. Rotate workers to limit individual cumulative manual handling tasks. Workers with musculoskeletal injuries must be assessed before this task.LowAll Workers / Site Supervisor
Struck by falling wall units during delivery or placementHighInspect all lifting equipment (chains, slings, clamps) prior to each lift. Use rated block-lifting clamps designed for the specific block profile. Establish exclusion zone of minimum 3 m from lifted load at all times. Workers must never walk under a suspended load. Tag lines to be used for load stabilisation during crane or excavator lifts. Stack delivered wall units on a firm, level surface, restrained by timber baulks or stakes. Do not stack sleepers or blocks more than 1.2 m high.LowRigger / Excavator Operator

Step 4Drainage and backfill installation

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Wall collapse due to inadequate or premature backfillingHighBackfilling must only commence once wall has achieved structural capacity as specified by the engineer (e.g. minimum 7-day concrete cure for cast-in-place walls, or after engineer-specified tie-back installation). Backfill in maximum 300 mm compacted lifts. Install drainage aggregate and ag drain pipe at every lift per drainage design before proceeding to the next lift. Do not use excavator bucket to push backfill directly against wall — use material spread at a distance then compact. Engineer to inspect each completed lift before next lift commences.ModerateSite Engineer / Site Supervisor

Step 5Working at height on top of retained embankment

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Falls from top of embankment or wallHighInstall compliant temporary edge protection (guardrail system to AS 1657 with top rail at 900–1100 mm, mid rail, and kickboard) at all embankment edges where the drop to the excavated level exceeds 2 m. Use a safety harness and inertia reel lanyard anchored to a rated anchor point when edge protection cannot be installed (e.g. during formwork stripping at wall face). Workers must not stand within 500 mm of an unprotected edge. Inspect edge protection at start of each shift.LowSite Supervisor / All Workers

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature

Get this template

Free. Edit the Excel version, or print the PDF and fill it in by hand.